Contract Upgrade and Migration Strategy

This document covers the strategy for upgrading deployed ProjectRegistry and InvestmentVault contracts while preserving on-chain state. It addresses issue #64.

Overview

Both contracts implement:

  • In-place WASM upgrade via upgrade(new_wasm_hash) — replaces bytecode while storage is preserved.
  • State schema versioning via STATE_VERSION constant, state_version(), stored_state_version(), and migrate_state(from_version).

The current schema version for both contracts is 1. Increment this constant whenever a storage layout change requires a migration step.

Storage Layout Versioning

Key Type Notes
StateVersion (instance) u32 Written at construction; read by require_current_state.

require_current_state rejects calls if the stored version does not match the compiled STATE_VERSION. This prevents accidentally running new logic against an old storage layout.

stored_state_version returns 0 for pre-versioned deployments (before v1 was introduced).

Contract-specific difference (verified against source, #275): ProjectRegistry's require_current_state special-cases a stored version of 0 as compatible and does not reject calls in that case (0 is treated as equivalent to v1, since the v0→v1 migration involved no layout changes). InvestmentVault's require_current_state has no such exception — it rejects any stored version that isn't exactly the current STATE_VERSION, including 0. Both contracts reject any other mismatched version identically.

Upgrade Procedure

Step 1 — Build the new WASM

stellar contract build
# Artifacts: target/wasm32v1-none/release/project_registry.wasm
#             target/wasm32v1-none/release/investment_vault.wasm

Run the full test suite before proceeding:

cargo test --all --quiet

Step 2 — Upload the new WASM

REGISTRY_HASH=$(stellar contract upload \
  --wasm target/wasm32v1-none/release/project_registry.wasm \
  --source "$STELLAR_SECRET_KEY" \
  --network testnet)

VAULT_HASH=$(stellar contract upload \
  --wasm target/wasm32v1-none/release/investment_vault.wasm \
  --source "$STELLAR_SECRET_KEY" \
  --network testnet)

Step 3 — Pause both contracts (recommended)

Before upgrading, pause user-facing operations to prevent state changes during the upgrade window:

stellar contract invoke --id "$REGISTRY_ID" --source "$STELLAR_SECRET_KEY" \
  --network testnet -- pause

stellar contract invoke --id "$VAULT_ID" --source "$STELLAR_SECRET_KEY" \
  --network testnet -- pause

Step 4 — Run the upgrade

Upgrade the registry first (vault depends on its interface):

stellar contract invoke --id "$REGISTRY_ID" --source "$STELLAR_SECRET_KEY" \
  --network testnet -- upgrade --new_wasm_hash "$REGISTRY_HASH"

stellar contract invoke --id "$VAULT_ID" --source "$STELLAR_SECRET_KEY" \
  --network testnet -- upgrade --new_wasm_hash "$VAULT_HASH"

Step 5 — Run state migration (if STATE_VERSION changed)

If STATE_VERSION was incremented (e.g., from 1 to 2), run migrate_state on each contract:

stellar contract invoke --id "$REGISTRY_ID" --source "$STELLAR_SECRET_KEY" \
  --network testnet -- migrate_state --from_version 1

stellar contract invoke --id "$VAULT_ID" --source "$STELLAR_SECRET_KEY" \
  --network testnet -- migrate_state --from_version 1

migrate_state panics with UnsupportedStateVersion if from_version does not match the stored version, preventing double-migration.

Step 6 — Verify and unpause

stellar contract invoke --id "$REGISTRY_ID" --source "$STELLAR_SECRET_KEY" \
  --network testnet -- stored_state_version
# Expected: 2 (or the new version)

stellar contract invoke --id "$VAULT_ID" --source "$STELLAR_SECRET_KEY" \
  --network testnet -- stored_state_version

stellar contract invoke --id "$REGISTRY_ID" --source "$STELLAR_SECRET_KEY" \
  --network testnet -- unpause

stellar contract invoke --id "$VAULT_ID" --source "$STELLAR_SECRET_KEY" \
  --network testnet -- unpause

Rollback

Soroban WASM upgrades are irreversible on-chain. The only rollback option is to re-upload and re-invoke upgrade with the previous WASM hash (which must have been retained). State written by the new version may be incompatible with the old WASM if the storage layout changed.

Best practice: keep all uploaded WASM hashes in deploy/testnet.json and always test migration end-to-end on testnet before mainnet.

Adding a New Storage Layout Version

When a storage layout change is required:

  1. Increment STATE_VERSION in the affected contract (e.g., from 1 to 2).
  2. Implement the migration logic inside migrate_state:
pub fn migrate_state(env: Env, from_version: u32) -> u32 {
    let current = read_state_version(&env);
    if current != from_version || current > STATE_VERSION {
        panic_with_error!(&env, RegistryError::UnsupportedStateVersion);
    }
    if current == 1 {
        // v1 → v2: example — populate new FooBar key from existing data
        // let old: OldType = env.storage().persistent().get(&DataKey::OldKey).unwrap();
        // env.storage().persistent().set(&DataKey::NewKey, &NewType::from(old));
        env.storage().instance().set(&DataKey::StateVersion, &2u32);
    }
    STATE_VERSION
}
  1. Write an integration test that exercises the full v(n-1) → vn path.
  2. Update this document with the new version entry.

Version History

Version Contract Description
0 Both Pre-versioning deployments (treat as v1 state layout).
1 Both Initial versioned deployment. No layout changes from v0.

Versioned Storage Patterns

  • Instance storage: use for small, frequently-read values (admin, counters). Billed per ledger close regardless of reads.
  • Persistent storage: use for per-project or per-address data. Billed only when entries exist; remove entries (not set-to-zero) when they become empty.
  • Temporary storage: not used; would be lost after ledger expiry.

Build Order for Cross-Contract Dependencies

The vault imports the registry ABI at build time via contractimport!. Always build and upload the registry before the vault when both change in the same release.

stellar contract build --package project-registry
stellar contract build --package investment-vault

Hard prerequisite — upgrading the vault before the registry is a point of no return. If the vault WASM is deployed first (calling registry.is_paused()) while the registry still runs old WASM (without that method), every fund_project call will fail with a host-level error until the registry is also upgraded. There is no automatic rollback. Always upgrade the registry first; only proceed to vault upgrade once registry.stored_state_version() confirms the new version is live.